A and B can complete a piece of work in 15 days and 20 days respectively. They work on alternate days, starting with A. In how many days will the work be completed?
- A. 12 days
- B. 15 days
- C. 25 days
- D. 17 days (Correct answer)
Correct Answer
Option D — 17 days
Detailed Solution & Explanation
17 days (Option D) — Take total work = LCM(15, 20) = 60 units. A's daily rate = 60/15 = 4 units/day and B's = 60/20 = 3 units/day. In each 2-day cycle (A then B), 4 + 3 = 7 units are finished. After 8 cycles (16 days), 8 x 7 = 56 units are done, leaving 4 units, which A completes on day 17. Therefore, Option D (17 days) is the verified correct response under Time & Work (Quantitative Aptitude).