Reasoning · SSC CGL 2026 Tier I — 30 Sep 2026 (Shift 2) · Last updated:

View the full solved paper: SSC CGL 2026 Tier I — 30 Sep 2026 (Shift 2)

3 people can do a job in 12 days. How many people are needed to finish it in 4 days?

  1. A. 6
  2. B. 8
  3. C. 9 (Correct answer)
  4. D. 12

Correct Answer

Option C — 9

Detailed Solution & Explanation

9 (Option C) — Total work required in person-days is 3 people x 12 days = 36 person-days. Because workforce size and completion time are inversely proportional for a fixed amount of work (M1 x D1 = M2 x D2), finishing 36 person-days in 4 days requires 36 / 4 = 9 people. Therefore, Option C (9) is the verified correct response under Time & Work (Reasoning).

Topics covered: Time & Work