Arrange the following key stages related to project clearance and compliance in India in chronological order (earliest first):
Environmental Legislation in India ·Previously asked in JKSSB Field Assistant 2026
View the full solved paper: JKSSB Field Assistant 2026 (Set A)
Question
Arrange the following key stages related to project clearance and compliance in India in chronological order (earliest first):
I. Grant of Environmental Clearance (EC)
II. Grant of Consent to Establish (CTE)
III. Construction and commissioning
IV. Grant of Consent to Operate (CTO)
Choose the correct sequence:
- A. II-I-III-IV
- B. I-II-III-IV (Correct answer)
- C. II-III-I-IV
- D. I-III-II-IV
Correct Answer
Option B — I-II-III-IV
Detailed Solution & Explanation
The correct answer per the official JKSSB final key is I-II-III-IV.
Key Points
- The regulatory sequence for an industrial project in India runs:
- I. Grant of Environmental Clearance (EC) — the project-level approval under the EIA Notification, 2006.
- II. Grant of Consent to Establish (CTE) — permission from the State Pollution Control Board to build.
- III. Construction and commissioning.
- IV. Grant of Consent to Operate (CTO) — permission to run, issued once the pollution control systems are in place and verified.
- The two fixed relationships are that CTO must come last, since it certifies installed controls, and that construction sits between the two consents.
Additional Information
- This item was among the ten reviewed after objections, and its key was revised from A (II-I-III-IV) to B (I-II-III-IV) — the change being whether environmental clearance or consent to establish comes first. The revision is sound: EC precedes CTE, because the State Board's consent is granted against a project that already holds clearance.
- The distinction between the two approvals is the heart of the sequence: EC is one-time and project-level, granted centrally or by SEIAA under the EPA 1986; consent is operational and renewable, granted by the SPCB under the Water and Air Acts.
- CTO is issued for a fixed term and must be renewed, which gives the Board a recurring point of leverage that a one-time clearance cannot provide.
- Obligations continue after commissioning through half-yearly compliance reports on the EMP and clearance conditions.
Topics covered: Project Clearance Chronology