Environmental Audit & Safety Audit · JKSSB Field Assistant 2026 (Set A) · Last updated:

View the full solved paper: JKSSB Field Assistant 2026 (Set A)

Arrange the following phases of an industrial disaster-management cycle in logical order (early to late):

  • I. Recovery
  • II. Response
  • III. Preparedness
  • IV. Prevention

Choose the correct sequence:

  1. A. IV-III-II-I (Correct answer)
  2. B. III-IV-II-I
  3. C. IV-II-III-I
  4. D. III-II-IV-I

Correct Answer

Option A — IV-III-II-I

Detailed Solution & Explanation

Key Points

  • The industrial disaster-management cycle runs in this order, early to late:
    • IV. Prevention — reduce or eliminate the hazard by design and siting.
    • III. Preparedness — plan, train and drill before anything happens.
    • II. Response — act during the emergency.
    • I. Recovery — restore and rehabilitate afterwards.
  • The logic is fixed by the event itself: two phases precede it, two follow it. Any option beginning with response or recovery inverts that and can be discarded at once.

Additional Information

  • It is a cycle rather than a line: lessons from recovery feed back into prevention for the next event, which is why it is drawn as a loop.
  • The distinction between the first two phases is the one most often tested — prevention removes the hazard, preparedness prepares for it. Safer plant design is prevention; a mock drill is preparedness.
  • Some frameworks add mitigation alongside prevention, covering measures that reduce severity where the hazard cannot be removed entirely — bunding around a storage tank, for instance.
  • India's Disaster Management Act, 2005 is explicitly built on this cycle, and the shift of national policy from response-centric to prevention-centric is its central theme.

Topics covered: Environmental Audit