Arrange the following phases of an industrial disaster-management cycle in logical order (early to late):
- I. Recovery
- II. Response
- III. Preparedness
- IV. Prevention
Choose the correct sequence:
- A. IV-III-II-I (Correct answer)
- B. III-IV-II-I
- C. IV-II-III-I
- D. III-II-IV-I
Correct Answer
Option A — IV-III-II-I
Detailed Solution & Explanation
Key Points
- The industrial disaster-management cycle runs in this order, early to late:
- IV. Prevention — reduce or eliminate the hazard by design and siting.
- III. Preparedness — plan, train and drill before anything happens.
- II. Response — act during the emergency.
- I. Recovery — restore and rehabilitate afterwards.
- The logic is fixed by the event itself: two phases precede it, two follow it. Any option beginning with response or recovery inverts that and can be discarded at once.
Additional Information
- It is a cycle rather than a line: lessons from recovery feed back into prevention for the next event, which is why it is drawn as a loop.
- The distinction between the first two phases is the one most often tested — prevention removes the hazard, preparedness prepares for it. Safer plant design is prevention; a mock drill is preparedness.
- Some frameworks add mitigation alongside prevention, covering measures that reduce severity where the hazard cannot be removed entirely — bunding around a storage tank, for instance.
- India's Disaster Management Act, 2005 is explicitly built on this cycle, and the shift of national policy from response-centric to prevention-centric is its central theme.
Topics covered: Environmental Audit