Arrange the following steps in a typical EIA process in logical sequence (earliest
Environmental Impact Assessment ·Previously asked in JKSSB Field Assistant 2026
View the full solved paper: JKSSB Field Assistant 2026 (Set A)
Question
Arrange the following steps in a typical EIA process in logical sequence (earliest
first):
L.
Decision-making and clearance
II. Environmental Impact Statement (EIS) preparation
III. Scoping and baseline study
IV. Screening and project identification
Choose the correct sequence:
- A. IV-III-II-I (Correct answer)
- B. III-IV-II-I
- C. IV-II-III-I
- D. III-II-IV-I
Correct Answer
Option A — IV-III-II-I
Detailed Solution & Explanation
The correct answer is IV-III-II-I.
Key Points
- The EIA process runs in a fixed logical order:
- IV. Screening and project identification — deciding whether an EIA is required at all.
- III. Scoping and baseline study — defining what to assess, then measuring existing conditions.
- II. Environmental Impact Statement preparation — compiling the findings into the report.
- I. Decision-making and clearance — the regulator grants, conditions or refuses approval.
- Each step supplies what the next one needs, so no other order is workable: you cannot scope before deciding an EIA is needed, cannot report before studying, and cannot decide before reading the report.
Additional Information
- The process does not end at clearance. Post-clearance monitoring and compliance reporting continue through construction and operation, with half-yearly reports to the regulator — the stage most often forgotten in exam answers.
- Between the EIS and the decision sits public consultation, comprising the public hearing at site and written submissions, and then appraisal by the expert committee.
- In India the four stages are named in the EIA Notification, 2006 as screening, scoping, public consultation and appraisal.
- Ordering questions of this type are quickest to settle by fixing the first and last items — screening must open and the decision must close — which usually eliminates every option but one.
Topics covered: EIA Process Chronology