Consider the following statements about sewage discharge and design periods:

Water & Waste Water Engineering ·Previously asked in JKSSB Field Assistant 2026

View the full solved paper: JKSSB Field Assistant 2026 (Set A)

Question

Consider the following statements about sewage discharge and design periods:

I. Per-capita sewage generated is generally taken as about 75-85% of per-capita water supplied.

II. The average daily sewage flow is sufficient for sizing all components of the sewerage system without any peak-factor consideration.

III. Design periods for sewers are usually longer than those for treatment-plant components.

Which of the statements given above is/are correct?

  1. A. I and II only
  2. B. I and III only (Correct answer)
  3. C. II and III only
  4. D. I, II and III

Correct Answer

Option B — I and III only

Detailed Solution & Explanation

The correct answer is I and III only.

Key Points

  • Statement I is correct. Per-capita sewage generation is conventionally taken as 75-85% of per-capita water supplied, the balance being consumptive losses.
  • Statement II is incorrect, and it is the deliberate error. The average daily flow does not size every component. Sewers and pumping mains are designed for peak flow, while self-cleansing velocity is checked at minimum flow — three different flows for three different checks.
  • Statement III is correct. Design periods differ by component precisely because the cost and disruption of later augmentation differ: long for buried sewers, shorter for expandable treatment units.

Additional Information

  • The peak factor falls as contributing population rises, because individual peaks in use no longer coincide. A small colony may need a factor near 3, a large city closer to 1.5.
  • Sizing on the average flow would under-design the sewer, causing surcharging and backflow into house connections during the morning peak — a failure that shows up immediately in service.
  • Conversely, sizing everything on the ultimate peak would leave early-year flows too shallow and slow to scour the invert, so solids deposit and generate hydrogen sulphide and crown corrosion.
  • Statement-based questions of this shape usually hide the error in an absolute word; here it is "all components".

Topics covered: Sewage Quantity Estimation Design Period