In rapid EIA, the level of prediction and analysis is generally:
Environmental Impact Assessment ·Previously asked in JKSSB Field Assistant 2026
View the full solved paper: JKSSB Field Assistant 2026 (Set A)
Question
In rapid EIA, the level of prediction and analysis is generally:
- A. Less detailed and more qualitative, often used for less-sensitive or small-scale (Correct answer)
- B. More detailed than comprehensive EIA
- C. Entirely based on secondary data only
- D. Only for international projects
Correct Answer
Option A — Less detailed and more qualitative, often used for less-sensitive or small-scale
Detailed Solution & Explanation
The correct answer is Less detailed and more qualitative, often used for limited data or preliminary assessment.
Key Points
- A Rapid EIA is the abbreviated form. It is based on one season's baseline data (excluding the monsoon) and relies more on qualitative judgement and secondary sources, producing a preliminary assessment quickly.
- A Comprehensive EIA covers all four seasons, giving a full year of baseline data and a far more detailed, quantitative analysis.
- The rejected options invert or overstate this: rapid EIA is less detailed than comprehensive, it does use primary data (just for a single season), and it is not restricted to international projects.
Additional Information
- The trade-off is time and cost against confidence. Rapid EIA allows a decision to be reached in months rather than a year, at the price of weaker seasonal coverage — which matters most where monsoon flows, migratory species or seasonal wind reversals govern the impact.
- Where a rapid EIA reveals significant impacts or serious data gaps, the appraisal authority can require it to be upgraded to a comprehensive study before granting clearance.
- The choice is made at the scoping stage and recorded in the Terms of Reference, so it is a regulatory decision rather than the consultant's own.
- The practical risk of rapid EIA is that a single season can systematically understate impacts — a river assessed only in the lean season looks very different from one assessed in spate.
Topics covered: Rapid and Comprehensive EIA EIA