Pumping stations for sewage are generally located:
Water & Waste Water Engineering ·Previously asked in JKSSB Field Assistant 2026
View the full solved paper: JKSSB Field Assistant 2026 (Set A)
Question
Pumping stations for sewage are generally located:
- A. Only at the extreme downstream end of the sewer network
- B. At depression points, along the sewer line, and at the sewage treatment plant head (Correct answer)
- C. Only at the start of the sewer line
- D. At random locations without any pattern
Correct Answer
Option B — At depression points, along the sewer line, and at the sewage treatment plant head
Detailed Solution & Explanation
The correct answer is At depression points, along the sewer line, and at the sewage treatment plant.
Key Points
- Sewers run by gravity, so pumping is introduced only where gravity flow cannot be sustained. That gives three characteristic locations:
- Depression points, where the ground falls and sewage collects in a low pocket from which it must be lifted;
- Along the sewer line, as intermediate lift stations, because a gravity sewer laid at a self-cleansing slope over a long distance would otherwise become impracticably deep;
- At the treatment plant, to lift incoming sewage to the head of the works so it can then flow by gravity through the successive treatment units.
- The other options are wrong because they confine pumping to a single point or deny any pattern at all.
Additional Information
- The controlling reason for intermediate lift stations is excavation depth and cost. A sewer must keep a minimum slope to stay self-cleansing, so over flat terrain it steadily deepens; lifting the sewage back near the surface restarts the gravity run at workable depth.
- A pumping station comprises a screen chamber and grit removal, a wet well providing storage, the pump house, a rising main and standby power, since a station that stops causes immediate overflow.
- Wet-well volume is chosen to limit pump starts per hour — frequent starting burns out motors — while remaining small enough that sewage does not turn septic during detention.
- Locating a station requires attention to odour and noise, which is why sites are chosen away from dense residential frontage where possible.
Topics covered: Pumping Stations Waste Water Engineering