A Disaster-Management Plan (DMP) in an industrial unit usually emphasizes:
Environmental Audit & Safety Audit ·Previously asked in JKSSB Field Assistant 2026
View the full solved paper: JKSSB Field Assistant 2026 (Set A)
Question
A Disaster-Management Plan (DMP) in an industrial unit usually emphasizes:
- A. Only fire-insurance settlement procedures
- B. Prevention, preparedness, response, and recovery across multiple hazards (Correct answer)
- C. Only weather-forecast downloading
- D. Only annual-holiday-planning
Correct Answer
Option B — Prevention, preparedness, response, and recovery across multiple hazards
Detailed Solution & Explanation
The correct answer is Prevention, preparedness, response, and recovery across multiple hazards.
Key Points
- A Disaster Management Plan is built around the four phases of the disaster-management cycle — prevention/mitigation, preparedness, response and recovery — and it addresses multiple hazards rather than a single scenario.
- In an industrial unit it therefore covers fire, explosion, toxic release, natural hazards such as earthquake and flood, and utility failures, integrating the on-site and off-site emergency plans within one framework.
- The rejected options each reduce it to a single administrative task.
Additional Information
- The four phases divide into pre-disaster activity (prevention and preparedness) and post-disaster activity (response and recovery), which is the framing used by the NDMA.
- Prevention eliminates or reduces the hazard through safer design and siting; preparedness builds the capacity to cope through plans, training and drills; response is the immediate action during the event; recovery restores operations and rehabilitates those affected.
- India's framework rests on the Disaster Management Act, 2005, establishing the NDMA under the Prime Minister, State authorities under Chief Ministers, and District Disaster Management Authorities under Collectors.