P and Q can do a piece of work in 20 days and 30 days, respectively. They work together for 6 days, and then Q is replaced by R.…
Quantitative Aptitude ·Previously asked in SSC CGL 2025
View the full solved paper: SSC CGL 2025 Tier II (19 Jan 2026)
Question
P and Q can do a piece of work in 20 days and 30 days, respectively. They work together for 6 days, and then Q is replaced by R. If the rest of the work is completed by P and R in 8 more days, in how many days can R alone complete 60% of the work?
- A. 28 days
- B. 48 days (Correct answer)
- C. 34 days
- D. 64 days
Correct Answer
Option B — 48 days
Detailed Solution & Explanation
The correct answer is 48 days.
Key Points
- Work done by P and Q together in 6 days:
- 6 × (1/20 + 1/30) = 6 × (3 + 2)/60 = 6 × 1/12 = 1/2 of the job
- The remaining 1/2 is finished by P and R in 8 days:
- 8 × (1/20 + 1/R) = 1/2
- 8/20 + 8/R = 1/2 → 2/5 + 8/R = 1/2 → 8/R = 1/10
- so R = 80 days for the whole job
- The question asks for 60% of the work: 0.6 × 80 = 48 days.
Additional Information
- Read the final line carefully — the answer is not R's time for the full job (80 days) but for 60% of it. That partial-work twist is the entire difficulty.
- Using an LCM of 60 units for the job gives the same result with whole numbers: P = 3 units/day, Q = 2, and R works out to 0.75 units/day, so 60 units take 80 days.
- Rates add, times do not — the commonest error in this topic is averaging the days.
- Where someone is *replaced* mid-task, split the work at that moment and treat the two stretches separately, exactly as here.
Topics covered: Time & Work Efficiency