Q98. 7 men and 15 women complete work in 15 days. 18 men and 20 women complete the same work in 8 days. X men and 20 women can co…
Quantitative Aptitude ·Previously asked in IBPS PO 2025
View the full solved paper: IBPS PO Pre 2025 Memory Based (23rd August, 1st Shift)
Question
Q98. 7 men and 15 women complete work in 15 days. 18 men and 20 women complete the same work in 8 days. X men and 20 women can complete the work in 10 days. Find X.
- A. 18
- B. 16
- C. 24
- D. 12 (Correct answer)
- E. 20
Correct Answer
Option D — 12
Detailed Solution & Explanation
The correct answer is 12.
Key Points
- 7m+15w=1/15 and 18m+20w=1/8. Solving: w=1/400, m=1/240.
- For X men + 20 women in 10 days: X/240 + 20/400 = 1/10 → X/240 = 1/20 → X=12.
Topics covered: IBPS PO Prelims 2025 Memory Based Quantitative Aptitude Time & Work