P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
- A. 8/15 (Correct answer)
- B. 7/15
- C. 11/15
- D. 2/11
Correct Answer
Option A — 8/15
Detailed Solution & Explanation
The correct answer is 8/15.
Key Points
- P's rate = 1/15 work/day.
- Q's rate = 1/20 work/day.
- Together per day = 1/15 + 1/20 = 4/60 + 3/60 = 7/60. In 4 days = 4 × 7/60 = 28/60 = 7/15. Work remaining = 1 − 7/15 = 8/15.