Three men A, B and C complete a work in 10 days, 12 days and 15 days respectively. All three of them start the work together. Aft…
Quantitative Aptitude ·Previously asked in JKSSB Junior Assistant 2026
View the full solved paper: JKSSB Junior Assistant PYQ
Question
Three men A, B and C complete a work in 10 days, 12 days and 15 days respectively. All three of them start the work together. After 2 days A left and after next 2 days C also left. Find in how many more days the whole work will be completed?
- A. 6 days
- B. 6 2/5 days (Correct answer)
- C. 6 3/5 days
- D. 6 4/5 days
Correct Answer
Option B — 6 2/5 days
Detailed Solution & Explanation
The correct answer is 6 2/5 days.
Key Points
- Total work = LCM(10, 12, 15) = 60 units; rates are A = 6, B = 5, C = 4 units/day.
- First 2 days all three work: (6+5+4)×2 = 30 units. Next 2 days B and C work (A has left): (5+4)×2 = 18 units — 48 units done.
- Remaining 12 units are done by B alone: 12 ÷ 5 = 2.4 days. Total = 2 + 2 + 2.4 = 6 2/5 days.
Exam tip
- Convert each worker's rate to a per-day fraction, add the rates of those working in each stage, and track the work stage by stage.
Additional Information
- Taking total work as LCM(10, 12, 15) = 60 units turns fractions into whole numbers: A does 6, B does 5 and C does 4 units a day.
- The LCM method is almost always faster and less error-prone than working with 1/10 + 1/12 + 1/15.
- Combined rate = 15 units a day, so all three together would finish in 4 days; the extra time comes from someone leaving partway.